As we now start the Measure Phase we must have a clear understanding of the current process.
To help us understand the process we needed to measure and document each stage of the changeover.
It was decided that firstly we should document every aspect of the changeover procedure no matter how small it appeared to be.
After collecting changeover data from several changeovers the detail involved in the process became surprisingly clear.
The team decided the best way to display the data was to input our data into a Gantt chart.
(see Fig 1 below).
We found this chart to be excellent in giving us a clear and accurate understanding of the time currently taken to complete each aspect of the changeovers.
![]() ![]() |
| Fig 1 |
Conclusions from Measure phase
- Currently takes 37 minutes from last spray cycle on Batch A to start of spray cycle on Batch B
- Cannot start PreWeigh on batch B until last unit on Batch A passes through Wet Weigh/Inspect due to CPU system constraint.
- Paperwork,Material Replenishment and clean down are done completely sequentially.
- Time taken for Tubing change and Nozzle clean by Engineering is 12 mins.
- 20 mins Drying time rule greatly restricts changeover time.
![]() |
| Fig 2 |
Basic Flowchart for reference (Fig 2)
![]() |
| Fig 3 |
![]() |
| Fig 4 |
![]() |
| Fig 5 |
Fig 5 shows spray machine external unit
Going forward to the Analysis phase
Going forward the key areas of focus will likely be on..
- Nozzle cleaning and Tubing change,
- Balancing of set up activities
- Constraints around CPU system and 20 min drying time